Differences between revisions 174 and 940 (spanning 766 versions)
Revision 174 as of 2017-11-29 09:21:29
Size: 7318
Comment:
Revision 940 as of 2019-07-31 13:33:39
Size: 23347
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
-----

== Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
== Schedule ==
2017/11/28 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}}


-----
------
<<Anchor(Meetings)>>
== Meetings ==

 . [[#1PMMeetings|1PM Daily Meeting]]
  * Zoom 1 URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]]
  * Time: 1PM, everyday
  * Location: KAGRA control room

 . [[#MorningMeetings|Morning Meeting]]
  * Zoom 1 URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]]
  * Time: 9AM, everyday
  * Location: KAGRA control room

 . [[#WeeklyMeetings|Weekly Meetings]]
  * Zoom 2 URL: [[https://zoom.us/j/6676627462|https://zoom.us/j/6676627462]]
  * Time: 11AM, every Tuesday
  * Location: 2F large meeting room

 . [[#OtherMeetings|Other Extra Meetings]]

----
Line 17: Line 25:
* 責任者  * [[https://teamup.com/kswnmta8p18h6u1uab|KAGRA Commissioning Planner]]


-----
-----
<<Anchor(1PMMeetings)>>
== Today's work plan: 2019/7/31 1PM - 2019/8/1 1PM ==
Commissioning leader: Miyakawa (July 29-30), Aso (August 1-3)

=== Afternoon ===
 * ITMY: BF work. (Okutomi, Sato, Fujii)
 * ITMY: H1 actuator investigation. (Ushiba, Yamada)

 * PEM: Reporting Temperature. (Yokozawa)
 * VAC, MIF: Opning GV, alingment. (Saito, Nakano, Michimura, Akutsu)
 * ASO: Small works at ETMX (Akutsu)
 * Replacing light source for IMMT2. (Akutsu)
 * Type B: Back to aligned mode. (Fabian)
 * DET: replacing OS of DET computer for offline analysis. (T.Yamamoto)
 * CAL: Xend Tcam will be touched. (Inoue)

=== Evening ===
 * IFO some work. (Nakano, Michimura, Akutsu)
 * VIS work can be done for Y arm work since Y arm is not available for a while. (Fujii, Okutomi)

=== Weekend ===
 

=== Morning ===
 * Releasing ITMY suspension. (Ushiba)
 * PSL work for grounding problem. (Nakano)
 * Maintenance for Ondotori at X-end (T.Yamamoto)


----
== Standing issues ==
 * Try FPPRMI: with stable 3f signals and ALS extra range, FPPRMI may fix the glitches?
 * Fast shut off feature on type-A after lockloss not to ring (real time model change, Stefan)
 * Y-arm lock
  * ETMY suspension control
  * ITMY damping
   * One IM magnet is broken. Need a different strategy. Use MN ? (Yamada, Okutomi)
  *
 * DRMI lock stability
  * Model HOM-PHD signal distortion (Aso, Kokeyama)
  * Search for better Gouy phase in PRC
 * Initial alignment automation (Nakano)
 * IFO configuration Guardian (Kokeyama)
 * SDF for all the VIS (Shoda, Okutomi)
 * Type-A related
  * Implement BF stage control on ALIGNED state on type-A guardian (Kokeyama)
  * United Guardian for all 4 suspensions (Okutomi)
  * Damping
  * Exchanging modified HPCD.
  * Type A: Feed forward technic to suppress extra motion (Nakano)
 * Type-B related
  * SR3 Yaw motion is too large (Fabian, Terrence)
 * Type-C related
  * OSEM characterization for OSTM (on going, Takahashi)
 * OMC
  * Replacing mirrors, alignment, etc.

 * Laser safety
  * Debug the laser safety guardian (Nakano)

 * IR QPD, centering on IR , green QPD at ETMY (Akutsu)
 * Exchanging laser source of oplev (Akutsu)


[[KAGRA/Commissioning/DailyMeetingArchive|Meeting archive]]

-----
-----
Line 19: Line 99:
 * PR系測定、PR2,PR3タンク蓋閉め
  * 11/16 木村、沢田、新井、*正田(蓋閉め)
  * 11/17 新井、*正田

 * Watchdog測定, PRM release
  * 11/20 *
  * 11/21 *
  * 11/22 *
  * 11/23 *

 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。

{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==

 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
}}}
-----

<<Anchor(Meetings)>>
-----
== Meetings ==

----
Line 57: Line 100:
=== Morning meeting === == Daily morning meeting ==
Line 60: Line 103:
 * Location: Control room, or educe


2017/11/29(Wed.)

 * Daily
  * 作業
   * WS
    * 機能に引き続き作業。色々進捗が報告されている。
    * MCの戻り光を干渉なしで直接見ても復調信号にオフセットが乗っているのでどうやらAMが載っているようである。WFSの出力がそれぞれのQuadrantでサインが違うなどいろいろおかしい。
    * 全てのFanを一旦切ってからノイズを測定し、その後戻したので、もし戻し忘れていることがないか気をつけてください。
    * PSL出射光でのビームが楕円になっている。今日一度きちんと見て見る。今日何か変更することはない。
   * Type Bp:
    * PRMのリリースが完了。IMまではそこそこアラインメントは戻っているはず。WDが飛んでいるようなのでBIOをつないでチェックが必要。
    * メインビームのアラインメント終了後3次元測定をする。

   * Type B:
    * BSのアラインメントを再度とる。ダンピング作業も続ける。
   * アラインメント
    * メインビームのアラインメントを今週再度とる。うまくけばPR系に光が行くはず。
    * COACH filterのアサインメントとクリーンエアーのを確認する必要がある。


  * 作業人員(*:責任者)
   * WS: *麻生、苔山、宮川 + 20名程度(見学+準備作業)
   * アラインメント: 和泉、正田、道村
   * Type Bp: 正田
   * Type B: Mark、 Enzo、平田、神津、Fabian


  * Laser hazard
   * 今日からSRラインより奥に変更。

 * Weekly
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直しと、リリース。
   * メインビームの再アラインメント。

  * 12/4の週
   * Type Aダンピングテスト。
  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。


 * 問題点など
  * D-SUBケーブルがおかしくなったものが出た。 -> AEL
  * 坑内計算機のリモート接続の改善要求(和泉、正田)。 -> DGS
  * 一部のカメラが表示されない(和泉、Stefan)。 -> 苔山
 * First ~10min in the morning meeting, as short as possible
 * Location: Control room and Fan hut connected by eZuce


=== 2019/7/31(Wed.) ===

==== Schedule ====
 * ~7/31: Trial for DRMI with polarization.
 * 7/6~: Trial for mass lock

 * ITMX

 * ETMX

 * ITMY

 * ETMY


 * Long term:
  * 7/1-8/9: FPMI/DRFPMI commissioning
  * 8/12-10/4: ASC
  * 10/7-11/15: Post Commissioning
  * 11/18-12/13: Noise hunting

==== Report of work ====
 * Finesse of X arm became low to ~1000.
  * Transmitted light was low.
  * ETMX has frost again.
  * We decided to turn off the cooler.

 * ITMY motor was stuck actually. It reached to one direction of the limit of range. It was fixed.
  * More continuous works are planed.
  * Magnet was not off. Needs more investigation.



==== Work plan ====
 * DGS maintenance for exchanging k1dc0, adding BIO cards to k1ioo1 for ALS control (Yamamoto, Oshino)
  * VIS should go safe mode. (Fabian)
  * DC power source will be exchanged at ALS0 and ALS1 rack. (Kamiizumi)
 * AOS: Checking and exchanging laser for oplev, ETMY or PRM.
 * Type B: Releasing FR for all suspensions after finishing maintenance or afternoon.
Line 115: Line 151:
---- -----
-----
Line 117: Line 154:
==== Weekly meeting ====
 * Date and time: Every Tuesday, 11AM
 * Location: Meeting room at Hokubukaikan, or eZuce, Polycom
=== Weekly meeting ===
Line 122: Line 158:
||76||2019/7/23||[[KAGRA/Commissioning/Weekly/20190723/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190723/Minute|Minute]]||||
||75||2019/7/16||[[KAGRA/Commissioning/Weekly/20190716/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190716/Minute|Minute]]||||
||74||2019/7/2||[[KAGRA/Commissioning/Weekly/20190702/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190702/Minute|Minute]]||||
||73||2019/6/25||[[KAGRA/Commissioning/Weekly/20190625/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190625/Minute|Minute]]||||
||72||2019/5/28||[[KAGRA/Commissioning/Weekly/20190528/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190528/Minute|Minute]]||||
||71||2019/5/21||[[KAGRA/Commissioning/Weekly/20190521/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190521/Minute|Minute]]||||
||70||2019/5/14||[[KAGRA/Commissioning/Weekly/20190514/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190514/Minute|Minute]]||||
||69||2019/5/7||[[KAGRA/Commissioning/Weekly/20190507/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190507/Minute|Minute]]||||
||68||2019/4/23||[[KAGRA/Commissioning/Weekly/20190423/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190423/Minute|Minute]]||||
||67||2019/4/16||[[KAGRA/Commissioning/Weekly/20190416/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190416/Minute|Minute]]||||
||66||2019/4/9||[[KAGRA/Commissioning/Weekly/20190409/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190409/Minute|Minute]]||||
||65-1||2019/4/2||[[KAGRA/Commissioning/Weekly/20190402/TypeA_Agenda|Integrated Type-A meeting]]|| || || ||
||65||2019/4/2||[[KAGRA/Commissioning/Weekly/20190402/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190402/Minute|Minute]]||||
||64||2019/3/26||[[KAGRA/Commissioning/Weekly/20190326/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190326/Minute|Minute]]||[[attachment:KAGRA/Commissioning/20190326_avoding_delay.pptx|file]]||
||63||2019/3/11||[[KAGRA/Commissioning/Weekly/20190311/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190311/Minute|Minute]]|| ||
||62||2019/3/5||[[KAGRA/Commissioning/Weekly/20190305/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190305/Minute|Minute]]|| ||
||61||2019/2/19||[[KAGRA/Commissioning/Weekly/20190219/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190219/Minute|Minute]]|| ||
||60||2019/2/5||[[KAGRA/Commissioning/Weekly/20190205/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190205/Minute|Minute]]|| ||
||59||2019/1/29||[[KAGRA/Commissioning/Weekly/20190129/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190129/Minute|Minute]]|| ||
||58||2019/1/22||[[KAGRA/Commissioning/Weekly/20190122/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190122/Minute|Minute]]|| ||
||57||2019/1/8||[[KAGRA/Commissioning/Weekly/20190108/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190108/Minute|Minute]]|| ||
||56||2018/12/25||[[KAGRA/Commissioning/Weekly/20181225/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181225/Minute|Minute]]|| ||
||55||2018/12/17||[[KAGRA/Commissioning/Weekly/20181217/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181217/Minute|Minute]]|| ||
||54||2018/12/11||[[KAGRA/Commissioning/Weekly/20181211/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181211/Minute|Minute]]|| ||
||53||2018/12/4 ||[[KAGRA/Commissioning/Weekly/20181204/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181204/Minute|Minute]]|| ||
||52||2018/11/27||[[KAGRA/Commissioning/Weekly/20181127/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181127/Minute|Minute]]|| ||
||51||2018/11/20||[[KAGRA/Commissioning/Weekly/20181120/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181120/Minute|Minute]]|| ||
||50||2018/11/13||[[KAGRA/Commissioning/Weekly/20181113/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181113/Minute|Minute]]|| ||
||49||2018/11/6 ||[[KAGRA/Commissioning/Weekly/20181105/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181105/Minute|Minute]]|| ||
||48||2018/10/30||[[KAGRA/Commissioning/Weekly/20181030/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181030/Minute|Minute]]|| ||
||47||2018/10/23||[[KAGRA/Commissioning/Weekly/20181023/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181023/Minute|Minute]]|| ||
||46||2018/10/16||[[KAGRA/Commissioning/Weekly/20181016/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181016/Minute|Minute]]|| ||
||45||2018/10/9 ||[[KAGRA/Commissioning/Weekly/20181009/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181009/Minute|Minute]]|| ||
||44||2018/10/2 ||[[KAGRA/Commissioning/Weekly/20181002/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181002/Minute|Minute]]|| ||
||43||2018/9/18 ||[[KAGRA/Commissioning/Weekly/20180918/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180918/Minute|Minute]]|| ||
||42||2018/9/4 ||[[KAGRA/Commissioning/Weekly/20180904/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180904/Minute|Minute]]|| ||
||41||2018/8/28 ||[[KAGRA/Commissioning/Weekly/20180828/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180828/Minute|Minute]]|| ||
||40||2018/8/21 ||[[KAGRA/Commissioning/Weekly/20180821/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180821.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180821/Minute|Minute]]|| ||
||39||2018/8/7 ||[[KAGRA/Commissioning/Weekly/20180807/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180807.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180807/Minute|Minute]]|| ||
||38||2018/7/31 ||[[KAGRA/Commissioning/Weekly/201807031/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180731.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180731/Minute|Minute]]|| ||
||37||2018/7/24 ||[[KAGRA/Commissioning/Weekly/201807024/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180724.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180724/Minute|Minute]]|| ||
||36||2018/7/17 ||[[KAGRA/Commissioning/Weekly/201807017/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180717.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180717/Minute|Minute]]|| ||
||35||2018/7/3 ||[[KAGRA/Commissioning/Weekly/20180703/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180703.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180703/Minute|Minute]]|| ||
||34||2018/6/26 ||[[KAGRA/Commissioning/Weekly/20180626/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180626.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180626/Minute|Minute]]|| ||
||33||2018/6/19 ||[[KAGRA/Commissioning/Weekly/20180619/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180619.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180619/Minute|Minute]]|| ||
||32||2018/6/12 ||[[KAGRA/Commissioning/Weekly/20180612/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180612.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180612/Minute|Minute]]|| ||
||31||2018/6/5 ||[[KAGRA/Commissioning/Weekly/20180605/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180605.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180605/Minute|Minute]]|| ||
||30||2018/5/22 ||[[KAGRA/Commissioning/Weekly/20180522/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180522.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180522/Minute|Minute]]|| ||
||29||2018/5/8 ||[[KAGRA/Commissioning/Weekly/20180508/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180508.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180508/Minute|Minute]]|| ||
||28||2018/5/1 ||[[KAGRA/Commissioning/Weekly/20180501/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180501.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180501/Minute|Minute]]|| ||
||27||2018/4/17 ||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| ||
||26||2018/4/10 ||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3 ||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27 ||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20 ||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13 ||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6 ||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27 ||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
||19||2018/2/20 ||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
||18||2018/2/13 ||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6 ||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30 ||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23 ||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16 ||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9 ||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
Line 128: Line 231:
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
Line 133: Line 236:
----
-----
-----
<<Anchor(OtherMeetings)>>
Line 135: Line 241:
 * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])
 * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])
 * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]


 * 2019/6/11: Summery meeting for E Run 1 [[/Meetings/Others/20190611/Agenda|Agenda]], [[KAGRA/Commissioning/Meetings/Others/20190611|Minute]]
 * 2019/6/5: Meeting for E Run on 6/8 [[/Meetings/Others/20190608/Agenda|Agenda]], [[KAGRA/Commissioning/Meetings/Others/20190608|Minute]]
 * 2019/3/8: Scheduling for FPMI [[/Meetings/Others/20190308/Agenda|Agenda]], [[KAGRA/Commissioning/Meetings/Others/20190308|Minute]]
 * 2018/9/3: Extended chief meeting for Arm commissioning [[/Meetings/Others/20180903/Agenda|Agenda]], [[KAGRA/Commissioning/Meetings/Others/20180903/Agenda/memo|Minute]]
 * 2018/8/30: 3rd Meeting for pump down at ITMX ([[/Meetings/Others/20180830|Minute]], [[/Phase2/Task/CheckList/VacuumITMX|Check list]])
 * 2018/8/23: 2nd Meeting for pump down at ITMX ([[/Meetings/Others/20180823|Minute]], [[/Phase2/Task/CheckList/VacuumITMX|Check list]])
 * 2018/8/16: Meeting for pump down at ITMX ([[/Meetings/Others/20180816|Minute]], [[/Phase2/Task/CheckList/VacuumITMX|Check list]])
 * 2018/5/28: [[KAGRA/Commissioning/Meetings/Others/20180528/Phase1|Meeting for looking back to phase1 for future of KAGRA]] as an extended chief meeting.
 * 2018/4/11: Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * 2018/4/5: Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * 2018/3/14: Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])
 * 2018/1/18: Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * 2018/1/17: Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * 2018/1/10: Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * 2017/12/13: Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * 2017/11/27~12/1[[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]
 * 2017/11/17: Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])
 * 2017/10/12: Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])


-----
-----
 
== Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]
 * [[https://docs.google.com/spreadsheets/d/1DSltWg18KrwnfkVJmSm09TkQ82aQ5lHAdaC9uCozGC0/edit?usp=sharing|Preparation for joining O3]]
Line 155: Line 285:
== Readiness for the X arm commissioning ==
 * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]]

KAGRA Commissioning Wiki


Meetings


Working people assignment



Today's work plan: 2019/7/31 1PM - 2019/8/1 1PM

Commissioning leader: Miyakawa (July 29-30), Aso (August 1-3)

Afternoon

  • ITMY: BF work. (Okutomi, Sato, Fujii)
  • ITMY: H1 actuator investigation. (Ushiba, Yamada)
  • PEM: Reporting Temperature. (Yokozawa)
  • VAC, MIF: Opning GV, alingment. (Saito, Nakano, Michimura, Akutsu)
  • ASO: Small works at ETMX (Akutsu)
  • Replacing light source for IMMT2. (Akutsu)
  • Type B: Back to aligned mode. (Fabian)
  • DET: replacing OS of DET computer for offline analysis. (T.Yamamoto)
  • CAL: Xend Tcam will be touched. (Inoue)

Evening

  • IFO some work. (Nakano, Michimura, Akutsu)
  • VIS work can be done for Y arm work since Y arm is not available for a while. (Fujii, Okutomi)

Weekend

Morning

  • Releasing ITMY suspension. (Ushiba)
  • PSL work for grounding problem. (Nakano)
  • Maintenance for Ondotori at X-end (T.Yamamoto)


Standing issues

  • Try FPPRMI: with stable 3f signals and ALS extra range, FPPRMI may fix the glitches?
  • Fast shut off feature on type-A after lockloss not to ring (real time model change, Stefan)
  • Y-arm lock
    • ETMY suspension control
    • ITMY damping
      • One IM magnet is broken. Need a different strategy. Use MN ? (Yamada, Okutomi)
  • DRMI lock stability
    • Model HOM-PHD signal distortion (Aso, Kokeyama)
    • Search for better Gouy phase in PRC
  • Initial alignment automation (Nakano)
  • IFO configuration Guardian (Kokeyama)
  • SDF for all the VIS (Shoda, Okutomi)
  • Type-A related
    • Implement BF stage control on ALIGNED state on type-A guardian (Kokeyama)
    • United Guardian for all 4 suspensions (Okutomi)
    • Damping
    • Exchanging modified HPCD.
    • Type A: Feed forward technic to suppress extra motion (Nakano)
  • Type-B related
    • SR3 Yaw motion is too large (Fabian, Terrence)
  • Type-C related
    • OSEM characterization for OSTM (on going, Takahashi)
  • OMC
    • Replacing mirrors, alignment, etc.
  • Laser safety
    • Debug the laser safety guardian (Nakano)
  • IR QPD, centering on IR , green QPD at ETMY (Akutsu)
  • Exchanging laser source of oplev (Akutsu)

Meeting archive



Daily morning meeting

  • Date and time: Every weekday, 9AM
  • First ~10min in the morning meeting, as short as possible
  • Location: Control room and Fan hut connected by eZuce

2019/7/31(Wed.)

Schedule

  • ~7/31: Trial for DRMI with polarization.
  • 7/6~: Trial for mass lock
  • ITMX
  • ETMX
  • ITMY
  • ETMY
  • Long term:
    • 7/1-8/9: FPMI/DRFPMI commissioning
    • 8/12-10/4: ASC
    • 10/7-11/15: Post Commissioning
    • 11/18-12/13: Noise hunting

Report of work

  • Finesse of X arm became low to ~1000.
    • Transmitted light was low.
    • ETMX has frost again.
    • We decided to turn off the cooler.
  • ITMY motor was stuck actually. It reached to one direction of the limit of range. It was fixed.
    • More continuous works are planed.
    • Magnet was not off. Needs more investigation.

Work plan

  • DGS maintenance for exchanging k1dc0, adding BIO cards to k1ioo1 for ALS control (Yamamoto, Oshino)
    • VIS should go safe mode. (Fabian)
    • DC power source will be exchanged at ALS0 and ALS1 rack. (Kamiizumi)
  • AOS: Checking and exchanging laser for oplev, ETMY or PRM.
  • Type B: Releasing FR for all suspensions after finishing maintenance or afternoon.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  



Weekly meeting

No.

Date

Agenda

Schedule

Minute

Files

76

2019/7/23

Agenda

See agenda page

Minute

75

2019/7/16

Agenda

See agenda page

Minute

74

2019/7/2

Agenda

See agenda page

Minute

73

2019/6/25

Agenda

See agenda page

Minute

72

2019/5/28

Agenda

See agenda page

Minute

71

2019/5/21

Agenda

See agenda page

Minute

70

2019/5/14

Agenda

See agenda page

Minute

69

2019/5/7

Agenda

See agenda page

Minute

68

2019/4/23

Agenda

See agenda page

Minute

67

2019/4/16

Agenda

See agenda page

Minute

66

2019/4/9

Agenda

See agenda page

Minute

65-1

2019/4/2

Integrated Type-A meeting

65

2019/4/2

Agenda

See agenda page

Minute

64

2019/3/26

Agenda

See agenda page

Minute

file

63

2019/3/11

Agenda

See agenda page

Minute

62

2019/3/5

Agenda

See agenda page

Minute

61

2019/2/19

Agenda

See agenda page

Minute

60

2019/2/5

Agenda

See agenda page

Minute

59

2019/1/29

Agenda

Minute

58

2019/1/22

Agenda

Minute

57

2019/1/8

Agenda

Minute

56

2018/12/25

Agenda

Minute

55

2018/12/17

Agenda

Minute

54

2018/12/11

Agenda

Minute

53

2018/12/4

Agenda

Minute

52

2018/11/27

Agenda

Minute

51

2018/11/20

Agenda

Minute

50

2018/11/13

Agenda

Minute

49

2018/11/6

Agenda

Minute

48

2018/10/30

Agenda

Minute

47

2018/10/23

Agenda

Minute

46

2018/10/16

Agenda

Minute

45

2018/10/9

Agenda

Schedule

Minute

44

2018/10/2

Agenda

Schedule

Minute

43

2018/9/18

Agenda

Schedule

Minute

42

2018/9/4

Agenda

Schedule

Minute

41

2018/8/28

Agenda

Schedule

Minute

40

2018/8/21

Agenda

Schedule

Minute

39

2018/8/7

Agenda

Schedule

Minute

38

2018/7/31

Agenda

Schedule

Minute

37

2018/7/24

Agenda

Schedule

Minute

36

2018/7/17

Agenda

Schedule

Minute

35

2018/7/3

Agenda

Schedule

Minute

34

2018/6/26

Agenda

Schedule

Minute

33

2018/6/19

Agenda

Schedule

Minute

32

2018/6/12

Agenda

Schedule

Minute

31

2018/6/5

Agenda

Schedule

Minute

30

2018/5/22

Agenda

Schedule

Minute

29

2018/5/8

Agenda

Schedule

Minute

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1



Other meetings



Task list


Documents

Communication tools

Readiness for the X arm commissioning


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)