20463
Comment:
|
22353
|
Deletions are marked like this. | Additions are marked like this. |
Line 3: | Line 3: |
=== Daily commissioning meeting === * Time: 1PM everyday * Location: KAGRA control room * Remote participation: https://zoom.us/j/7631499341 ---- == Today's work plan: 2019/7/17 1PM - 2019/7/18 1PM == Commissioning leader: Aso (July 17th-19th) === Afternoon === * ETMY HP coil driver check (Takahashi, Yamada) * Watchdog, Output resistance, Cable resistance, Take a picture of the PCB * Check the maximum current acceptable by the in-vac cable. * Calculate theoretical limit (Ushiba) * AS alignment (Kokeyama et al) * SR3 OSEM check (Fabian, Terrence) * Y-arm mass lock trial (SB, EY, MN, et al) * ISS work (Yoshioka, Nakano) === Evening === * Y-arm mass lock trial (SB, EY, MN, et al) * Type-A guardian work on ETMX (Kokeyama) * DRMI investigation ? (SB, EY, MN, et al) === Morning === * HP coil driver modification ? (Yamada, Fabian, Terrence) ---- == Standing issues == * Y-arm lock * ETMY suspension control * !L2Angle decoupling * ETMY coil driver range increase * DRMI lock stability * Model HOM-PHD signal distortion (Aso, Kokeyama) * Search for better Gouy phase in PRC * Initial alignment automation * Type-A related * Add aligned state in Guardian (Kokeyama) * Type-B related * SR3 Yaw motion is too large * Different ground level between the IO chasis and the AA filter box may be the reason * Replace the DC power supply * Type-C related * OSEM characterization for OSTM * OMC * Check the OMC on the AS table * Laser safety * Debug the laser safety guardian ------ |
|
Line 53: | Line 109: |
=== 2019/7/1(Tue.) === | === 2019/7/17(Wed.) === |
Line 56: | Line 112: |
* --(6/18 Move PR3)-- * 6/19: DRMI locked. * 6/21: polarization issue found. |
* ~7/31: Trial for DRMI with polarization. * 7/6~: Trial for mass lock |
Line 64: | Line 118: |
* 6/21: Stop cooler. | |
Line 69: | Line 122: |
* 6/20: Stop cooler * 6/28: Open chamber |
|
Line 74: | Line 125: |
* --(4/22-5/31: Yarm commissioning)-- | |
Line 83: | Line 133: |
* Please reduce the number or speed of 16kHz channels. | * We have 1pm meeting more seriously. It will discuss next 24 house commissioning plan. * Please write down klog when your work is done and if you will have something to be announced. |
Line 90: | Line 141: |
* Type A: ETMY was fixed by opening chamber. Clamp was added to be more tight. * Needs light to fix position. * Surface of ITMY was fogged on Sunday. We need to check and wait for a while. * CRT: closing ETMY after alignment done * COM: Try to lock PRX for checking beam shape. |
* Y arm mass lock had some progress on suppressing error signal. Not |
Line 97: | Line 144: |
* DMG: Try to connect to the additional space on second E18. * Type A: Oplev of ITMY seems to be something wrong and it will be fixed |
* Coil driver for mass lock will be upgrade to have more current. * SR3 noise will be checked and probably power supply will be exchanged. * OMC will be extracted in the morning. * DGS: maintenance for exchanging DC power supply for IO chassis for SR3 and SR2. * Team PC exchange will be postponed. * Type A model will be restarted. |
Line 112: | Line 162: |
||75||2019/7/16||[[KAGRA/Commissioning/Weekly/20190716/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190716/Minute|Minute]]|||| ||74||2019/7/2||[[KAGRA/Commissioning/Weekly/20190702/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190702/Minute|Minute]]|||| |
KAGRA Commissioning Wiki
Daily commissioning meeting
- Time: 1PM everyday
- Location: KAGRA control room
Remote participation: https://zoom.us/j/7631499341
Today's work plan: 2019/7/17 1PM - 2019/7/18 1PM
Commissioning leader: Aso (July 17th-19th)
Afternoon
- ETMY HP coil driver check (Takahashi, Yamada)
- Watchdog, Output resistance, Cable resistance, Take a picture of the PCB
- Check the maximum current acceptable by the in-vac cable.
- Calculate theoretical limit (Ushiba)
- AS alignment (Kokeyama et al)
- SR3 OSEM check (Fabian, Terrence)
- Y-arm mass lock trial (SB, EY, MN, et al)
- ISS work (Yoshioka, Nakano)
Evening
- Y-arm mass lock trial (SB, EY, MN, et al)
- Type-A guardian work on ETMX (Kokeyama)
- DRMI investigation ? (SB, EY, MN, et al)
Morning
- HP coil driver modification ? (Yamada, Fabian, Terrence)
Standing issues
- Y-arm lock
- ETMY suspension control
L2Angle decoupling
- ETMY coil driver range increase
- ETMY suspension control
- DRMI lock stability
- Model HOM-PHD signal distortion (Aso, Kokeyama)
- Search for better Gouy phase in PRC
- Initial alignment automation
- Type-A related
- Add aligned state in Guardian (Kokeyama)
- Type-B related
- SR3 Yaw motion is too large
- Different ground level between the IO chasis and the AA filter box may be the reason
- Replace the DC power supply
- SR3 Yaw motion is too large
- Type-C related
- OSEM characterization for OSTM
- OMC
- Check the OMC on the AS table
- Laser safety
- Debug the laser safety guardian
Task list
Schedule
Working people assignment
Readiness for the X arm commissioning
https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing
Meetings
Daily Meetings (9AM, 1PM)
Zoom URL: https://zoom.us/j/7631499341
Weekly Meetings (Tuesday 11AM)
Zoom URL: https://zoom.us/j/6676627462
Daily meeting
- Date and time: Every weekday, 9AM
- First ~10min in the morning meeting, as short as possible
- Location: Control room and Fan hut connected by eZuce
2019/7/17(Wed.)
Schedule
- ~7/31: Trial for DRMI with polarization.
- 7/6~: Trial for mass lock
- ITMX
- ETMX
- ITMY
- ETMY
- Long term:
5/27-6/30: DRMI commissioning
- 7/1-8/9: FPMI/DRFPMI commissioning
- 8/12-10/4: ASC
- 10/7-11/15: Post Commissioning
- 11/18-12/13: Noise hunting
Note
- We have 1pm meeting more seriously. It will discuss next 24 house commissioning plan.
- Please write down klog when your work is done and if you will have something to be announced.
Night work
Weekend
Report of work
- Y arm mass lock had some progress on suppressing error signal. Not
Work plan
- Coil driver for mass lock will be upgrade to have more current.
- SR3 noise will be checked and probably power supply will be exchanged.
- OMC will be extracted in the morning.
- DGS: maintenance for exchanging DC power supply for IO chassis for SR3 and SR2.
- Team PC exchange will be postponed.
- Type A model will be restarted.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or Zoom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
75 |
2019/7/16 |
See agenda page |
|||
74 |
2019/7/2 |
See agenda page |
|||
73 |
2019/6/25 |
See agenda page |
|||
72 |
2019/5/28 |
See agenda page |
|||
71 |
2019/5/21 |
See agenda page |
|||
70 |
2019/5/14 |
See agenda page |
|||
69 |
2019/5/7 |
See agenda page |
|||
68 |
2019/4/23 |
See agenda page |
|||
67 |
2019/4/16 |
See agenda page |
|||
66 |
2019/4/9 |
See agenda page |
|||
65-1 |
2019/4/2 |
|
|
|
|
65 |
2019/4/2 |
See agenda page |
|||
64 |
2019/3/26 |
See agenda page |
|||
63 |
2019/3/11 |
See agenda page |
|
||
62 |
2019/3/5 |
See agenda page |
|
||
61 |
2019/2/19 |
See agenda page |
|
||
60 |
2019/2/5 |
See agenda page |
|
||
59 |
2019/1/29 |
|
|
||
58 |
2019/1/22 |
|
|
||
57 |
2019/1/8 |
|
|
||
56 |
2018/12/25 |
|
|
||
55 |
2018/12/17 |
|
|
||
54 |
2018/12/11 |
|
|
||
53 |
2018/12/4 |
|
|
||
52 |
2018/11/27 |
|
|
||
51 |
2018/11/20 |
|
|
||
50 |
2018/11/13 |
|
|
||
49 |
2018/11/6 |
|
|
||
48 |
2018/10/30 |
|
|
||
47 |
2018/10/23 |
|
|
||
46 |
2018/10/16 |
|
|
||
45 |
2018/10/9 |
|
|||
44 |
2018/10/2 |
|
|||
43 |
2018/9/18 |
|
|||
42 |
2018/9/4 |
|
|||
41 |
2018/8/28 |
|
|||
40 |
2018/8/21 |
|
|||
39 |
2018/8/7 |
|
|||
38 |
2018/7/31 |
|
|||
37 |
2018/7/24 |
|
|||
36 |
2018/7/17 |
|
|||
35 |
2018/7/3 |
|
|||
34 |
2018/6/26 |
|
|||
33 |
2018/6/19 |
|
|||
32 |
2018/6/12 |
|
|||
31 |
2018/6/5 |
|
|||
30 |
2018/5/22 |
|
|||
29 |
2018/5/8 |
|
|||
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
2018/9/3: Extended chief meeting for Arm commissioning Agenda, Minute
2018/8/30: 3rd Meeting for pump down at ITMX (Minute, Check list)
2018/8/23: 2nd Meeting for pump down at ITMX (Minute, Check list)
2018/8/16: Meeting for pump down at ITMX (Minute, Check list)
2018/5/28: Meeting for looking back to phase1 for future of KAGRA as an extended chief meeting.
2018/4/11: Meeting for pump down test at ETMX 2 (Minute, Check list)
2018/4/5: Meeting for pump down test at ETMX 1 (Minute, Check list)
2018/3/14: Meeting for pump down test at Center are (Minute, Check list)
2018/1/18: Meeting for pump down and cooling at ETMY3 (Minute, Check list)
2018/1/17: Meeting for pump down and cooling at ETMY2 (Minute, Check list)
2018/1/10: Meeting for pump down and cooling at ETMY1 (Minute, Check list)
2017/12/13: Meeting for pump down at ETMY (Minute, schedule)
2017/11/27~12/1Commissioning Workshop 2017
2017/11/17: Meeting for closing ETY (Minute)
2017/10/12: Meeting about PR2 pitch misalignment (Minute)