KAGRA Commissioning Wiki
Daily commissioning meeting
- Time: 1PM everyday
- Location: KAGRA control room
Remote participation: https://zoom.us/j/7631499341
Today's work plan: 2019/7/16 1PM - 2019/7/17 1PM
Commissioning leader: Miyakawa (July 16th), Aso (July 17th)
Afternoon
ETMY L2Angle decoupling (Yamada, Nakano)
- Check the schematic of the High Power Coil Driver (Fabian, Terrence)
- Fix the CARM board boost issue (Enomoto)
- Design a filter for DARM (Stefan)
Evening
- Y-arm mass lock trial (SB, EY, MN, et al)
Morning
- DGS maintenance
- Power supply replacement of SR3 (Yamamoto)
- ITM T-cam computer replacement (Yokozawa)
- OMC extraction (Aso, et al)
- Check dimensions around OSTM (Takahashi)
Standing issues
- Y-arm lock
- ETMY suspension control
L2Angle decoupling
- ETMY coil driver range increase
- CARM board boost does not engage
- ETMY suspension control
- DRMI lock stability
- Model HOM-PHD signal distortion (Aso, Kokeyama)
- Search for better Gouy phase in PRC
- Initial alignment automation
- Type-A related
- Add aligned state in Guardian (Kokeyama)
- Type-B related
- SR3 Yaw motion is too large
- Different ground level between the IO chasis and the AA filter box may be the reason
- Replace the DC power supply
- BS IM2TM transfer function measurement
- SR3 Yaw motion is too large
- Type-C related
- Check dimensions around the OSTM
- OSEM characterization for OSTM
- OMC
- Extract OMC
- Check the OMC on the AS table
- Laser safety
- Debug the laser safety guardian
Task list
Schedule
Working people assignment
Readiness for the X arm commissioning
https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing
Meetings
Daily Meetings (9AM, 1PM)
Zoom URL: https://zoom.us/j/7631499341
Weekly Meetings (Tuesday 11AM)
Zoom URL: https://zoom.us/j/6676627462
Daily meeting
- Date and time: Every weekday, 9AM
- First ~10min in the morning meeting, as short as possible
- Location: Control room and Fan hut connected by eZuce
2019/7/16(Tue.)
Schedule
- ~7/31: Trial for DRMI with polarization.
- 7/6~: Trial for mass lock
- ITMX
- ETMX
- ITMY
- 7/4: Turbo pump on
- ETMY
- 7/4: Turbo pump on
- Long term:
4/22-5/31: Yarm commissioning
5/27-6/30: DRMI commissioning
- 7/1-8/9: FPMI/DRFPMI commissioning
- 8/12-10/4: ASC
- 10/7-11/15: Post Commissioning
- 11/18-12/13: Noise hunting
Note
Night work
Weekend
Report of work
- OMC: Beam spot on mirror moved. One (or more) of the mirrors seems to be misaligned. OMC will be pulled tomorrow.
- Y arm: 20dB suppression on LSC below 1Hz was seen on mass lock trial.
- Opleve control was slightly changed from IM control to TM control.
- High frequency is limited by noise. Needs high power coil driver modification.
- Type B: H2 on SR3 was noisy, but needs more time to investigate it.
- 80mHz peak was reduced by changing damping setting.
- RTPC for ASC and ALS were dead somehow.
Work plan
KAGRA/Commissioning/DailyWork << < 2025 / 5 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | |||
5 | 6 | 7 | 8 | 9 | 10 | 11 |
12 | 13 | 14 | 15 | 16 | 17 | 18 |
19 | 20 | 21 | 22 | 23 | 24 | 25 |
26 | 27 | 28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or Zoom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
75 |
2019/7/16 |
See agenda page |
|||
74 |
2019/7/2 |
See agenda page |
|||
73 |
2019/6/25 |
See agenda page |
|||
72 |
2019/5/28 |
See agenda page |
|||
71 |
2019/5/21 |
See agenda page |
|||
70 |
2019/5/14 |
See agenda page |
|||
69 |
2019/5/7 |
See agenda page |
|||
68 |
2019/4/23 |
See agenda page |
|||
67 |
2019/4/16 |
See agenda page |
|||
66 |
2019/4/9 |
See agenda page |
|||
65-1 |
2019/4/2 |
|
|
|
|
65 |
2019/4/2 |
See agenda page |
|||
64 |
2019/3/26 |
See agenda page |
|||
63 |
2019/3/11 |
See agenda page |
|
||
62 |
2019/3/5 |
See agenda page |
|
||
61 |
2019/2/19 |
See agenda page |
|
||
60 |
2019/2/5 |
See agenda page |
|
||
59 |
2019/1/29 |
|
|
||
58 |
2019/1/22 |
|
|
||
57 |
2019/1/8 |
|
|
||
56 |
2018/12/25 |
|
|
||
55 |
2018/12/17 |
|
|
||
54 |
2018/12/11 |
|
|
||
53 |
2018/12/4 |
|
|
||
52 |
2018/11/27 |
|
|
||
51 |
2018/11/20 |
|
|
||
50 |
2018/11/13 |
|
|
||
49 |
2018/11/6 |
|
|
||
48 |
2018/10/30 |
|
|
||
47 |
2018/10/23 |
|
|
||
46 |
2018/10/16 |
|
|
||
45 |
2018/10/9 |
|
|||
44 |
2018/10/2 |
|
|||
43 |
2018/9/18 |
|
|||
42 |
2018/9/4 |
|
|||
41 |
2018/8/28 |
|
|||
40 |
2018/8/21 |
|
|||
39 |
2018/8/7 |
|
|||
38 |
2018/7/31 |
|
|||
37 |
2018/7/24 |
|
|||
36 |
2018/7/17 |
|
|||
35 |
2018/7/3 |
|
|||
34 |
2018/6/26 |
|
|||
33 |
2018/6/19 |
|
|||
32 |
2018/6/12 |
|
|||
31 |
2018/6/5 |
|
|||
30 |
2018/5/22 |
|
|||
29 |
2018/5/8 |
|
|||
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
2018/9/3: Extended chief meeting for Arm commissioning Agenda, Minute
2018/8/30: 3rd Meeting for pump down at ITMX (Minute, Check list)
2018/8/23: 2nd Meeting for pump down at ITMX (Minute, Check list)
2018/8/16: Meeting for pump down at ITMX (Minute, Check list)
2018/5/28: Meeting for looking back to phase1 for future of KAGRA as an extended chief meeting.
2018/4/11: Meeting for pump down test at ETMX 2 (Minute, Check list)
2018/4/5: Meeting for pump down test at ETMX 1 (Minute, Check list)
2018/3/14: Meeting for pump down test at Center are (Minute, Check list)
2018/1/18: Meeting for pump down and cooling at ETMY3 (Minute, Check list)
2018/1/17: Meeting for pump down and cooling at ETMY2 (Minute, Check list)
2018/1/10: Meeting for pump down and cooling at ETMY1 (Minute, Check list)
2017/12/13: Meeting for pump down at ETMY (Minute, schedule)
2017/11/27~12/1Commissioning Workshop 2017
2017/11/17: Meeting for closing ETY (Minute)
2017/10/12: Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools