[[KAGRA/Commissioning/DailyMeetingArchive|Meeting archive]] ---- == Today's work plan: 2019/7/22 1PM - 2019/7/23 1PM == Commissioning leader: Miyakawa (22nd-26th) |
Line 15: | Line 17: |
* DRMI OLT measurement (SB, MN, VF) * Xend - Photon calibrator BIO card fix (Inoue) * Pcal injection test (Inoue) * Alert monitor grace DB in Mozumi computer room (Urchen) * Fabian and Shimode-san will check the temperature raise, analog WD, etc for the coil driver change |
* PEM: 320.5Hz noise (Yokozawa) * Preparation for fiber noise cancellation (Enomoto, Sugimoto) * This turns on air filters. * OMC control (Kokeyama, Darkhan) * ALS hand over to IR(Stefan, Valera, Nakano) |
Line 22: | Line 24: |
* DARM OLT measurement (MN, VF) * If coil driver modification ready, arm commissioning === Morning === |
* ALS hand over to IR (Stefan, Valera, Nakano) * DRFPMI lock (Stefan, Valera, Nakano) === Weekend === === Morning (Monday) === * ITMY damping (Okutomi) |
Line 27: | Line 32: |
* Fix SRM oplev bad position (Fabian) * PEM IXC seis acc measurement (Yokozawa) ---- == Today's work plan: 2019/7/17 1PM - 2019/7/18 1PM == Commissioning leader: Aso (July 17th-19th) === Afternoon === * ETMY HP coil driver check (Takahashi, Yamada) * Watchdog, Output resistance, Cable resistance, Take a picture of the PCB * Check the maximum current acceptable by the in-vac cable. * Calculate theoretical limit (Ushiba) * AS alignment (Kokeyama et al) * SR3 OSEM check (Fabian, Terrence) * Y-arm mass lock trial (SB, EY, MN, et al) * ISS work (Yoshioka, Nakano) === Evening === * Y-arm mass lock trial (SB, EY, MN, et al) * Type-A guardian work on ETMX (Kokeyama) * DRMI investigation ? (SB, EY, MN, et al) * Found Y end coil needed more range, more drive for MN (dominate 10Hz sensing noise limited, cross over) Note * DC feedback works perfect * Tcam alignment system is done (see from camera screen) * ALIGNED guardian on ETMX (test phase) === Morning === * HP coil driver modification ? (Yamada, Fabian, Terrence) |
* DGS maintenance for k1asc0. * Adding BIO card to k1als0, k1ioo1. * Exchanging old type modified HPCD. (Ushiba, Takahashi) * ISS control servo (Yoshioka, Kokeyama) |
Line 64: | Line 40: |
* X end cry cooler replaced. EX frige can be operated. Plan to be decided tomorrow. * DGS maintenance maybe better on Monday morning? |
|
Line 69: | Line 43: |
* !L2Angle decoupling * ETMY coil driver range increase |
* ITMY damping * One IM magnet is broken. Need a different strategy. Use MN ? (Yamada, Okutomi) * |
Line 74: | Line 49: |
* Initial alignment automation | * Initial alignment automation (Nakano) * IFO configuration Guardian (Kokeyama) |
Line 76: | Line 52: |
* Guardian modification according to the coil driver modification * Implement BF stage control on ALINED state on type-A guardian |
* Implement BF stage control on ALIGNED state on type-A guardian (Kokeyama) * United Guardian for all 4 suspensions (Okutomi) * Damping * Exchanging modified HPCD. * Type A: Feed forward technic to suppress extra motion (Nakano) |
Line 79: | Line 58: |
* SR3 Yaw motion is too large * Different ground level between the IO chasis and the AA filter box may be the reason * Replace the DC power supply |
* SR3 Yaw motion is too large (Fabian, Terrence) |
Line 83: | Line 60: |
* OSEM characterization for OSTM | * OSEM characterization for OSTM (on going, Takahashi) |
Line 87: | Line 64: |
* Debug the laser safety guardian | * Debug the laser safety guardian (Nakano) * IR QPD, centering on IR , green QPD at ETMY (Akutsu) * AS tube installation on 7/30-31 (Michimura) * Valve unit exchange for ITMX on 7/26 for 1-2 hours (Kimura) * Fiber noise cancellation on Saturday (Enomoto, Sugimoto) |
Line 135: | Line 118: |
== Daily meeting == | == Daily morning meeting == |
Line 142: | Line 125: |
=== 2019/7/17(Wed.) === | === 2019/7/23(Tue.) === |
Line 158: | Line 141: |
* --(5/27-6/30: DRMI commissioning)-- | |
Line 166: | Line 148: |
* We have 1pm meeting more seriously. It will discuss next 24 house commissioning plan. * Please write down klog when your work is done and if you will have something to be announced. |
|
Line 174: | Line 154: |
* Y arm mass lock had some progress on suppressing error signal. Not | * ALS DARM was succeeded last night with 30Hz RMS. Target is ~20Hz. * SR3 has some noise H2 OSEM. It is being traced. * Mode matching OMC using independent laser outside. It will be connected control today. |
Line 177: | Line 159: |
* Coil driver for mass lock will be upgrade to have more current. * SR3 noise will be checked and probably power supply will be exchanged. * OMC will be extracted in the morning. * DGS: maintenance for exchanging DC power supply for IO chassis for SR3 and SR2. * Team PC exchange will be postponed. * Type A model will be restarted. |
|
Line 195: | Line 172: |
||76||2019/7/23||[[KAGRA/Commissioning/Weekly/20190723/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190723/Minute|Minute]]|||| |
KAGRA Commissioning Wiki
Daily commissioning meeting
- Time: 1PM everyday
- Location: KAGRA control room
Remote participation: https://zoom.us/j/7631499341
Today's work plan: 2019/7/22 1PM - 2019/7/23 1PM
Commissioning leader: Miyakawa (22nd-26th)
Afternoon
- PEM: 320.5Hz noise (Yokozawa)
- Preparation for fiber noise cancellation (Enomoto, Sugimoto)
- This turns on air filters.
- OMC control (Kokeyama, Darkhan)
- ALS hand over to IR(Stefan, Valera, Nakano)
Evening
- ALS hand over to IR (Stefan, Valera, Nakano)
- DRFPMI lock (Stefan, Valera, Nakano)
Weekend
Morning (Monday)
- ITMY damping (Okutomi)
- SR3 OSEM check (Fabian)
- DGS maintenance for k1asc0.
- Adding BIO card to k1als0, k1ioo1.
- Exchanging old type modified HPCD. (Ushiba, Takahashi)
- ISS control servo (Yoshioka, Kokeyama)
Standing issues
- Try FPPRMI: with stable 3f signals and ALS extra range, FPPRMI may fix the glitches?
- Fast shut off feature on type-A after lockloss not to ring (real time model change, Stefan)
- Y-arm lock
- ETMY suspension control
- ITMY damping
- One IM magnet is broken. Need a different strategy. Use MN ? (Yamada, Okutomi)
- DRMI lock stability
- Model HOM-PHD signal distortion (Aso, Kokeyama)
- Search for better Gouy phase in PRC
- Initial alignment automation (Nakano)
- IFO configuration Guardian (Kokeyama)
- Type-A related
- Implement BF stage control on ALIGNED state on type-A guardian (Kokeyama)
- United Guardian for all 4 suspensions (Okutomi)
- Damping
- Exchanging modified HPCD.
- Type A: Feed forward technic to suppress extra motion (Nakano)
- Type-B related
- SR3 Yaw motion is too large (Fabian, Terrence)
- Type-C related
- OSEM characterization for OSTM (on going, Takahashi)
- OMC
- Check the OMC on the AS table
- Laser safety
- Debug the laser safety guardian (Nakano)
- IR QPD, centering on IR , green QPD at ETMY (Akutsu)
- AS tube installation on 7/30-31 (Michimura)
- Valve unit exchange for ITMX on 7/26 for 1-2 hours (Kimura)
- Fiber noise cancellation on Saturday (Enomoto, Sugimoto)
Task list
Schedule
Working people assignment
Readiness for the X arm commissioning
https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing
Meetings
Daily Meetings (9AM, 1PM)
Zoom URL: https://zoom.us/j/7631499341
Weekly Meetings (Tuesday 11AM)
Zoom URL: https://zoom.us/j/6676627462
Daily morning meeting
- Date and time: Every weekday, 9AM
- First ~10min in the morning meeting, as short as possible
- Location: Control room and Fan hut connected by eZuce
2019/7/23(Tue.)
Schedule
- ~7/31: Trial for DRMI with polarization.
- 7/6~: Trial for mass lock
- ITMX
- ETMX
- ITMY
- ETMY
- Long term:
- 7/1-8/9: FPMI/DRFPMI commissioning
- 8/12-10/4: ASC
- 10/7-11/15: Post Commissioning
- 11/18-12/13: Noise hunting
Note
Night work
Weekend
Report of work
- ALS DARM was succeeded last night with 30Hz RMS. Target is ~20Hz.
- SR3 has some noise H2 OSEM. It is being traced.
- Mode matching OMC using independent laser outside. It will be connected control today.
Work plan
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or Zoom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
76 |
2019/7/23 |
See agenda page |
|||
75 |
2019/7/16 |
See agenda page |
|||
74 |
2019/7/2 |
See agenda page |
|||
73 |
2019/6/25 |
See agenda page |
|||
72 |
2019/5/28 |
See agenda page |
|||
71 |
2019/5/21 |
See agenda page |
|||
70 |
2019/5/14 |
See agenda page |
|||
69 |
2019/5/7 |
See agenda page |
|||
68 |
2019/4/23 |
See agenda page |
|||
67 |
2019/4/16 |
See agenda page |
|||
66 |
2019/4/9 |
See agenda page |
|||
65-1 |
2019/4/2 |
|
|
|
|
65 |
2019/4/2 |
See agenda page |
|||
64 |
2019/3/26 |
See agenda page |
|||
63 |
2019/3/11 |
See agenda page |
|
||
62 |
2019/3/5 |
See agenda page |
|
||
61 |
2019/2/19 |
See agenda page |
|
||
60 |
2019/2/5 |
See agenda page |
|
||
59 |
2019/1/29 |
|
|
||
58 |
2019/1/22 |
|
|
||
57 |
2019/1/8 |
|
|
||
56 |
2018/12/25 |
|
|
||
55 |
2018/12/17 |
|
|
||
54 |
2018/12/11 |
|
|
||
53 |
2018/12/4 |
|
|
||
52 |
2018/11/27 |
|
|
||
51 |
2018/11/20 |
|
|
||
50 |
2018/11/13 |
|
|
||
49 |
2018/11/6 |
|
|
||
48 |
2018/10/30 |
|
|
||
47 |
2018/10/23 |
|
|
||
46 |
2018/10/16 |
|
|
||
45 |
2018/10/9 |
|
|||
44 |
2018/10/2 |
|
|||
43 |
2018/9/18 |
|
|||
42 |
2018/9/4 |
|
|||
41 |
2018/8/28 |
|
|||
40 |
2018/8/21 |
|
|||
39 |
2018/8/7 |
|
|||
38 |
2018/7/31 |
|
|||
37 |
2018/7/24 |
|
|||
36 |
2018/7/17 |
|
|||
35 |
2018/7/3 |
|
|||
34 |
2018/6/26 |
|
|||
33 |
2018/6/19 |
|
|||
32 |
2018/6/12 |
|
|||
31 |
2018/6/5 |
|
|||
30 |
2018/5/22 |
|
|||
29 |
2018/5/8 |
|
|||
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
2018/9/3: Extended chief meeting for Arm commissioning Agenda, Minute
2018/8/30: 3rd Meeting for pump down at ITMX (Minute, Check list)
2018/8/23: 2nd Meeting for pump down at ITMX (Minute, Check list)
2018/8/16: Meeting for pump down at ITMX (Minute, Check list)
2018/5/28: Meeting for looking back to phase1 for future of KAGRA as an extended chief meeting.
2018/4/11: Meeting for pump down test at ETMX 2 (Minute, Check list)
2018/4/5: Meeting for pump down test at ETMX 1 (Minute, Check list)
2018/3/14: Meeting for pump down test at Center are (Minute, Check list)
2018/1/18: Meeting for pump down and cooling at ETMY3 (Minute, Check list)
2018/1/17: Meeting for pump down and cooling at ETMY2 (Minute, Check list)
2018/1/10: Meeting for pump down and cooling at ETMY1 (Minute, Check list)
2017/12/13: Meeting for pump down at ETMY (Minute, schedule)
2017/11/27~12/1Commissioning Workshop 2017
2017/11/17: Meeting for closing ETY (Minute)
2017/10/12: Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools