----- === Daily commissioning meeting === * Time: 1PM everyday * Location: KAGRA control room * Remote participation: https://zoom.us/j/7631499341 [[KAGRA/Commissioning/DailyMeetingArchive|Meeting archive]] |
------ <<Anchor(Meetings)>> == Meetings == . [[#1PMMeetings|1PM Daily Meeting]] * Zoom 1 URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]] * Time: 1PM, everyday * Location: KAGRA control room . [[#MorningMeetings|Morning Meeting]] * Zoom 1 URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]] * Time: 9AM, everyday * Location: KAGRA control room . [[#WeeklyMeetings|Weekly Meetings]] * Zoom 2 URL: [[https://zoom.us/j/6676627462|https://zoom.us/j/6676627462]] * Time: 11AM, every Tuesday * Location: 2F large meeting room . [[#OtherMeetings|Other Extra Meetings]] |
Line 13: | Line 24: |
== Today's work plan: 2019/7/19 1PM - 2019/7/22 1PM == Commissioning leader: Aso (19th), Miyakawa (22nd) |
== Working people assignment == * [[https://teamup.com/kswnmta8p18h6u1uab|KAGRA Commissioning Planner]] ----- ----- <<Anchor(1PMMeetings)>> == Today's work plan: 2019/7/25 1PM - 2019/7/26 1PM == Commissioning leader: Miyakawa (22nd-26th) |
Line 17: | Line 35: |
* Exchanging HPCD(Fabian, Washimini) * check the range of new HPCD using oplev (Valera, Nakano). * ITMY damping (Okutomi) * ALS sweep to find IR resonance (MN, VF) * TEMP00 lock with dither(Nakano). |
* Monitor for venting ITMY (Okutomi) * Updating RT model for Type A, except for ITMY (Okutomi) * ASC test on ITMX (Ushiba) * ETMX work (Fujii) * SR3 work for control loop IM yaw (Fabian) * OMC characterization with control (Kokeyama, Somiya) * Fiber noise cancellation on Saturday (Enomoto, Sugimoto) * ISS put wind shield outside PSL (Yoshioka, Kukromiya) * Pick up Moku:Lab (Guiguo) * Stop venting around the evening (Ushiba) * Checking cable noise for PEM (T.Takana) * PEM: Vibration measurement at IXC (Yokozawa) * Measurement for PRs (Shoda) |
Line 24: | Line 51: |
* ALS sweep to find IR resonance (MN, VF) * DRMI lock (Stefan) |
* Fiber noise cancellation on Saturday (Enomoto) |
Line 28: | Line 54: |
=== Morning (Monday) === * ITMY damping (Okutomi) * SR3 OSEM check (Fabian) * Type A: Feed forward technic to suppress extra motion (Nakano) |
* Xarm ALS hand over to IR using TR (Enomoto) * Fiber noise cancellation on Saturday (Enomoto, Sugimoto) === Monday Morning === * ITMY damping (Okutomi) * Type A work (Fujii) * ITMX damping (Ushiba) * Cryo cooler valve exchange (Kimura, Ushiba) * SR3 TF measurement (Fabian) * Automation for SR3 and SRM (Shoda) * Noise source by cable or something in the center room (Yokozawa) * Setting magnet meter at Y end (Yokozawa) |
Line 49: | Line 81: |
* SDF for all the VIS (Shoda, Okutomi) | |
Line 60: | Line 93: |
* Check the OMC on the AS table | * OMC characterization with control |
Line 64: | Line 98: |
* AS tube installation on 7/30-31 (Michimura) * Valve unit exchange for ITMX on 7/26 for 1-2 hours (Kimura) * Fiber noise cancellation on Saturday (Enomoto, Sugimoto) * ITM noise measurement by PEM on 27th morning (Yokozawa). |
|
Line 65: | Line 105: |
------ == Task list == * [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] * [[https://docs.google.com/spreadsheets/d/1DSltWg18KrwnfkVJmSm09TkQ82aQ5lHAdaC9uCozGC0/edit?usp=sharing|Preparation for joining O3]] ----- <<Anchor(Schedule)>> === Schedule === ----- == Working people assignment == * [[https://teamup.com/kswnmta8p18h6u1uab|KAGRA Commissioning Planner]] == Readiness for the X arm commissioning == * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]] |
* Exchanging laser source of oplev (Akutsu) [[KAGRA/Commissioning/DailyMeetingArchive|Meeting archive]] ----- ----- |
Line 90: | Line 113: |
{{{#!wiki comment/dotted ----- <<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == }}} ----- <<Anchor(Meetings)>> == Meetings == ==== Daily Meetings (9AM, 1PM) ==== Zoom URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]] ==== Weekly Meetings (Tuesday 11AM) ==== Zoom URL: [[https://zoom.us/j/6676627462|https://zoom.us/j/6676627462]] ---- |
|
Line 111: | Line 114: |
== Daily meeting == | == Daily morning meeting == |
Line 118: | Line 121: |
=== 2019/7/22(Wed.) === | === 2019/7/26(Fri.) === |
Line 141: | Line 144: |
* We have 1pm meeting more seriously. It will discuss next 24 house commissioning plan. * Please write down klog when your work is done and if you will have something to be announced. |
|
Line 149: | Line 150: |
* IOO: Demodulator for iMC was exchanged as a part of CALM loop (Enomoto). * A new IFO configuration was implemented. |
* COM: Hand off to TRX was succeeded in! * ITMY: F0 motor on ITMY was stuck. * We decided to open the chamber to fix the motor. * One of the dropped magnet of IM on ITMY will be glued. * It seemed to be another magnet was off. * OMC axis was not perfect, but it is turned out not easy to tune the axis by hand without jig. |
Line 153: | Line 158: |
* SR3 needs some work for noise hunting. * OMC work. |
* Remaining TF of ITMY will be measured this morning. * Cryo cooler valve exchange (Kimura, Ushiba) * Venting will start. * Type A work (Fujii) * SR3 TF measurement (Fabian) * Automation for SR3 and SRM (Shoda) * Noise source by cable or something in the center room (Yokozawa) * Setting magnet meter at Y end (Yokozawa) |
Line 160: | Line 172: |
---- | ----- ----- |
Line 163: | Line 176: |
* Date and time: Every Tuesday, 11AM * Location: Meeting room at Hokubukaikan, or Zoom |
|
Line 168: | Line 179: |
||76||2019/7/23||[[KAGRA/Commissioning/Weekly/20190723/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190723/Minute|Minute]]|||| | |
Line 245: | Line 257: |
---- | ----- ----- <<Anchor(OtherMeetings)>> |
Line 269: | Line 284: |
----- == Task list == * [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] * [[https://docs.google.com/spreadsheets/d/1DSltWg18KrwnfkVJmSm09TkQ82aQ5lHAdaC9uCozGC0/edit?usp=sharing|Preparation for joining O3]] ----- |
|
Line 283: | Line 306: |
== Readiness for the X arm commissioning == * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]] |
KAGRA Commissioning Wiki
Meetings
Zoom 1 URL: https://zoom.us/j/7631499341
- Time: 1PM, everyday
- Location: KAGRA control room
Zoom 1 URL: https://zoom.us/j/7631499341
- Time: 9AM, everyday
- Location: KAGRA control room
Zoom 2 URL: https://zoom.us/j/6676627462
- Time: 11AM, every Tuesday
- Location: 2F large meeting room
Working people assignment
Today's work plan: 2019/7/25 1PM - 2019/7/26 1PM
Commissioning leader: Miyakawa (22nd-26th)
Afternoon
- Monitor for venting ITMY (Okutomi)
- Updating RT model for Type A, except for ITMY (Okutomi)
- ASC test on ITMX (Ushiba)
- ETMX work (Fujii)
- SR3 work for control loop IM yaw (Fabian)
- OMC characterization with control (Kokeyama, Somiya)
- Fiber noise cancellation on Saturday (Enomoto, Sugimoto)
- ISS put wind shield outside PSL (Yoshioka, Kukromiya)
Pick up Moku:Lab (Guiguo)
- Stop venting around the evening (Ushiba)
- Checking cable noise for PEM (T.Takana)
- PEM: Vibration measurement at IXC (Yokozawa)
- Measurement for PRs (Shoda)
Evening
- Fiber noise cancellation on Saturday (Enomoto)
Weekend
- Xarm ALS hand over to IR using TR (Enomoto)
- Fiber noise cancellation on Saturday (Enomoto, Sugimoto)
Monday Morning
- ITMY damping (Okutomi)
- Type A work (Fujii)
- ITMX damping (Ushiba)
- Cryo cooler valve exchange (Kimura, Ushiba)
- SR3 TF measurement (Fabian)
- Automation for SR3 and SRM (Shoda)
- Noise source by cable or something in the center room (Yokozawa)
- Setting magnet meter at Y end (Yokozawa)
Standing issues
- Try FPPRMI: with stable 3f signals and ALS extra range, FPPRMI may fix the glitches?
- Fast shut off feature on type-A after lockloss not to ring (real time model change, Stefan)
- Y-arm lock
- ETMY suspension control
- ITMY damping
- One IM magnet is broken. Need a different strategy. Use MN ? (Yamada, Okutomi)
- DRMI lock stability
- Model HOM-PHD signal distortion (Aso, Kokeyama)
- Search for better Gouy phase in PRC
- Initial alignment automation (Nakano)
- IFO configuration Guardian (Kokeyama)
- SDF for all the VIS (Shoda, Okutomi)
- Type-A related
- Implement BF stage control on ALIGNED state on type-A guardian (Kokeyama)
- United Guardian for all 4 suspensions (Okutomi)
- Damping
- Exchanging modified HPCD.
- Type A: Feed forward technic to suppress extra motion (Nakano)
- Type-B related
- SR3 Yaw motion is too large (Fabian, Terrence)
- Type-C related
- OSEM characterization for OSTM (on going, Takahashi)
- OMC
- OMC characterization with control
- Laser safety
- Debug the laser safety guardian (Nakano)
- AS tube installation on 7/30-31 (Michimura)
- Valve unit exchange for ITMX on 7/26 for 1-2 hours (Kimura)
- Fiber noise cancellation on Saturday (Enomoto, Sugimoto)
- ITM noise measurement by PEM on 27th morning (Yokozawa).
- IR QPD, centering on IR , green QPD at ETMY (Akutsu)
- Exchanging laser source of oplev (Akutsu)
Daily morning meeting
- Date and time: Every weekday, 9AM
- First ~10min in the morning meeting, as short as possible
- Location: Control room and Fan hut connected by eZuce
2019/7/26(Fri.)
Schedule
- ~7/31: Trial for DRMI with polarization.
- 7/6~: Trial for mass lock
- ITMX
- ETMX
- ITMY
- ETMY
- Long term:
- 7/1-8/9: FPMI/DRFPMI commissioning
- 8/12-10/4: ASC
- 10/7-11/15: Post Commissioning
- 11/18-12/13: Noise hunting
Note
Night work
Weekend
Report of work
- COM: Hand off to TRX was succeeded in!
- ITMY: F0 motor on ITMY was stuck.
- We decided to open the chamber to fix the motor.
- One of the dropped magnet of IM on ITMY will be glued.
- It seemed to be another magnet was off.
- OMC axis was not perfect, but it is turned out not easy to tune the axis by hand without jig.
Work plan
- Remaining TF of ITMY will be measured this morning.
- Cryo cooler valve exchange (Kimura, Ushiba)
- Venting will start.
- Type A work (Fujii)
- SR3 TF measurement (Fabian)
- Automation for SR3 and SRM (Shoda)
- Noise source by cable or something in the center room (Yokozawa)
- Setting magnet meter at Y end (Yokozawa)
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
76 |
2019/7/23 |
See agenda page |
|||
75 |
2019/7/16 |
See agenda page |
|||
74 |
2019/7/2 |
See agenda page |
|||
73 |
2019/6/25 |
See agenda page |
|||
72 |
2019/5/28 |
See agenda page |
|||
71 |
2019/5/21 |
See agenda page |
|||
70 |
2019/5/14 |
See agenda page |
|||
69 |
2019/5/7 |
See agenda page |
|||
68 |
2019/4/23 |
See agenda page |
|||
67 |
2019/4/16 |
See agenda page |
|||
66 |
2019/4/9 |
See agenda page |
|||
65-1 |
2019/4/2 |
|
|
|
|
65 |
2019/4/2 |
See agenda page |
|||
64 |
2019/3/26 |
See agenda page |
|||
63 |
2019/3/11 |
See agenda page |
|
||
62 |
2019/3/5 |
See agenda page |
|
||
61 |
2019/2/19 |
See agenda page |
|
||
60 |
2019/2/5 |
See agenda page |
|
||
59 |
2019/1/29 |
|
|
||
58 |
2019/1/22 |
|
|
||
57 |
2019/1/8 |
|
|
||
56 |
2018/12/25 |
|
|
||
55 |
2018/12/17 |
|
|
||
54 |
2018/12/11 |
|
|
||
53 |
2018/12/4 |
|
|
||
52 |
2018/11/27 |
|
|
||
51 |
2018/11/20 |
|
|
||
50 |
2018/11/13 |
|
|
||
49 |
2018/11/6 |
|
|
||
48 |
2018/10/30 |
|
|
||
47 |
2018/10/23 |
|
|
||
46 |
2018/10/16 |
|
|
||
45 |
2018/10/9 |
|
|||
44 |
2018/10/2 |
|
|||
43 |
2018/9/18 |
|
|||
42 |
2018/9/4 |
|
|||
41 |
2018/8/28 |
|
|||
40 |
2018/8/21 |
|
|||
39 |
2018/8/7 |
|
|||
38 |
2018/7/31 |
|
|||
37 |
2018/7/24 |
|
|||
36 |
2018/7/17 |
|
|||
35 |
2018/7/3 |
|
|||
34 |
2018/6/26 |
|
|||
33 |
2018/6/19 |
|
|||
32 |
2018/6/12 |
|
|||
31 |
2018/6/5 |
|
|||
30 |
2018/5/22 |
|
|||
29 |
2018/5/8 |
|
|||
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
2018/9/3: Extended chief meeting for Arm commissioning Agenda, Minute
2018/8/30: 3rd Meeting for pump down at ITMX (Minute, Check list)
2018/8/23: 2nd Meeting for pump down at ITMX (Minute, Check list)
2018/8/16: Meeting for pump down at ITMX (Minute, Check list)
2018/5/28: Meeting for looking back to phase1 for future of KAGRA as an extended chief meeting.
2018/4/11: Meeting for pump down test at ETMX 2 (Minute, Check list)
2018/4/5: Meeting for pump down test at ETMX 1 (Minute, Check list)
2018/3/14: Meeting for pump down test at Center are (Minute, Check list)
2018/1/18: Meeting for pump down and cooling at ETMY3 (Minute, Check list)
2018/1/17: Meeting for pump down and cooling at ETMY2 (Minute, Check list)
2018/1/10: Meeting for pump down and cooling at ETMY1 (Minute, Check list)
2017/12/13: Meeting for pump down at ETMY (Minute, schedule)
2017/11/27~12/1Commissioning Workshop 2017
2017/11/17: Meeting for closing ETY (Minute)
2017/10/12: Meeting about PR2 pitch misalignment (Minute)
Task list
Documents
Communication tools
Readiness for the X arm commissioning
https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing