Differences between revisions 823 and 902 (spanning 79 versions)
Revision 823 as of 2019-07-22 13:34:59
Size: 22460
Comment:
Revision 902 as of 2019-07-26 13:23:07
Size: 23923
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
-----

=== Daily commissioning meeting ===
 * Time: 1PM everyday
 * Location: KAGRA control room
 * Remote participation: https://zoom.us/j/7631499341

[[KAGRA/Commissioning/DailyMeetingArchive|Meeting archive]]
------
<<Anchor(Meetings)>>
== Meetings ==

 . [[#1PMMeetings|1PM Daily Meeting]]
  * Zoom 1 URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]]
  * Time: 1PM, everyday
  * Location: KAGRA control room

 . [[#MorningMeetings|Morning Meeting]]
  * Zoom 1 URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]]
  * Time: 9AM, everyday
  * Location: KAGRA control room

 . [[#WeeklyMeetings|Weekly Meetings]]
  * Zoom 2 URL: [[https://zoom.us/j/6676627462|https://zoom.us/j/6676627462]]
  * Time: 11AM, every Tuesday
  * Location: 2F large meeting room

 . [[#OtherMeetings|Other Extra Meetings]]
Line 13: Line 24:
== Today's work plan: 2019/7/19 1PM - 2019/7/22 1PM ==
Commissioning leader: Aso (19th), Miyakawa (22nd)
== Working people assignment ==
 * [[https://teamup.com/kswnmta8p18h6u1uab|KAGRA Commissioning Planner]]


-----
-----
<<Anchor(1PMMeetings)>>
== Today's work plan: 2019/7/25 1PM - 2019/7/26 1PM ==
Commissioning leader: Miyakawa (22nd-26th)
Line 17: Line 35:
 * Exchanging HPCD(Fabian, Washimini)
  * check the range of new HPCD using oplev (Valera, Nakano).
 * ITMY damping (Okutomi)
 * ALS sweep to find IR resonance (MN, VF)
  * TEMP00 lock with dither(Nakano).
 * Monitor for venting ITMY (Okutomi)
  * Updating RT model for Type A, except for ITMY (Okutomi)
 * ASC test on ITMX (Ushiba)
 * ETMX work (Fujii)
 * SR3 work for control loop IM yaw (Fabian)
 * OMC characterization with control (Kokeyama, Somiya)
 * Fiber noise cancellation on Saturday (Enomoto, Sugimoto)
 * ISS put wind shield outside PSL (Yoshioka, Kukromiya)
 * Pick up Moku:Lab (Guiguo)
 * Stop venting around the evening (Ushiba)
 * Checking cable noise for PEM (T.Takana)
 * PEM: Vibration measurement at IXC (Yokozawa)
 * Measurement for PRs (Shoda)
Line 24: Line 51:
 * ALS sweep to find IR resonance (MN, VF)
 * DRMI lock (Stefan)
 * Fiber noise cancellation on Saturday (Enomoto)
Line 28: Line 54:

=== Morning (Monday) ===
 * ITMY damping (Okutomi)
 * SR3 OSEM check (Fabian)
 * Type A: Feed forward technic to suppress extra motion (Nakano)
 * Fiber noise cancellation work at PSL on Saturday (Enomoto, Sugimoto)
 * Xarm ALS hand over to IR using TR (Enomoto)

=== Monday Morning ===
 * ITMY damping (Okutomi)
 * Type A work (Fujii)
 * ITMX damping (Ushiba)
 * Cryo cooler valve exchange (Kimura, Ushiba)
 * SR3 TF measurement (Fabian)
 * Automation for SR3 and SRM (Shoda)
 * Noise source by cable or something in the center room (Yokozawa)
 * Setting magnet meter at Y end (Yokozawa)
Line 49: Line 81:
 * SDF for all the VIS (Shoda, Okutomi)
Line 60: Line 93:
  * Check the OMC on the AS table   * OMC characterization with control
Line 64: Line 98:

 * AS tube installation on 7/30-31 (Michimura)
 * Valve unit exchange for ITMX on 7/26 for 1-2 hours (Kimura)
 * Fiber noise cancellation on Saturday (Enomoto, Sugimoto)
 * ITM noise measurement by PEM on 27th morning (Yokozawa).
Line 65: Line 105:
------
 
 

== Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]
 * [[https://docs.google.com/spreadsheets/d/1DSltWg18KrwnfkVJmSm09TkQ82aQ5lHAdaC9uCozGC0/edit?usp=sharing|Preparation for joining O3]]

-----
<<Anchor(Schedule)>>
=== Schedule ===




-----
== Working people assignment ==
 * [[https://teamup.com/kswnmta8p18h6u1uab|KAGRA Commissioning Planner]]

== Readiness for the X arm commissioning ==
 * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]]
 * Exchanging laser source of oplev (Akutsu)


[[KAGRA/Commissioning/DailyMeetingArchive|Meeting archive]]

-----
-----
Line 90: Line 113:
{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==


}}}
-----

<<Anchor(Meetings)>>

== Meetings ==

==== Daily Meetings (9AM, 1PM) ====
Zoom URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]]

==== Weekly Meetings (Tuesday 11AM) ====
Zoom URL: [[https://zoom.us/j/6676627462|https://zoom.us/j/6676627462]]

----
Line 111: Line 114:
== Daily meeting == == Daily morning meeting ==
Line 118: Line 121:
=== 2019/7/22(Wed.) === === 2019/7/26(Fri.) ===
Line 141: Line 144:
 * We have 1pm meeting more seriously. It will discuss next 24 house commissioning plan.
 * Please write down klog when your work is done and if you will have something to be announced.
Line 149: Line 150:
 * IOO: Demodulator for iMC was exchanged as a part of CALM loop (Enomoto).
 * A new IFO configuration was implemented.
 * COM: Hand off to TRX was succeeded in!
 * ITMY: F0 motor on ITMY was stuck.
  * We decided to open the chamber to fix the motor.
  * One of the dropped magnet of IM on ITMY will be glued.
  * It seemed to be another magnet was off.
 * OMC axis was not perfect, but it is turned out not easy to tune the axis by hand without jig.
Line 153: Line 158:
 * SR3 needs some work for noise hunting.
 * OMC work.
 * Remaining TF of ITMY will be measured this morning.
 * Cryo cooler valve exchange (Kimura, Ushiba)
 * Venting will start.
 * Type A work (Fujii)

 * SR3 TF measurement (Fabian)
 * Automation for SR3 and SRM (Shoda)

 * Noise source by cable or something in the center room (Yokozawa)
 * Setting magnet meter at Y end (Yokozawa)
Line 160: Line 172:
---- -----
-----
Line 163: Line 176:
 * Date and time: Every Tuesday, 11AM
 * Location: Meeting room at Hokubukaikan, or Zoom
Line 168: Line 179:
||76||2019/7/23||[[KAGRA/Commissioning/Weekly/20190723/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190723/Minute|Minute]]||||
Line 245: Line 257:
----
-----
-----
<<Anchor(OtherMeetings)>>
Line 269: Line 284:
-----
 
== Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]
 * [[https://docs.google.com/spreadsheets/d/1DSltWg18KrwnfkVJmSm09TkQ82aQ5lHAdaC9uCozGC0/edit?usp=sharing|Preparation for joining O3]]
-----
Line 283: Line 306:
== Readiness for the X arm commissioning ==
 * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]]

KAGRA Commissioning Wiki


Meetings


Working people assignment



Today's work plan: 2019/7/25 1PM - 2019/7/26 1PM

Commissioning leader: Miyakawa (22nd-26th)

Afternoon

  • Monitor for venting ITMY (Okutomi)
    • Updating RT model for Type A, except for ITMY (Okutomi)
  • ASC test on ITMX (Ushiba)
  • ETMX work (Fujii)
  • SR3 work for control loop IM yaw (Fabian)
  • OMC characterization with control (Kokeyama, Somiya)
  • Fiber noise cancellation on Saturday (Enomoto, Sugimoto)
  • ISS put wind shield outside PSL (Yoshioka, Kukromiya)
  • Pick up Moku:Lab (Guiguo)

  • Stop venting around the evening (Ushiba)
  • Checking cable noise for PEM (T.Takana)
  • PEM: Vibration measurement at IXC (Yokozawa)
  • Measurement for PRs (Shoda)

Evening

  • Fiber noise cancellation on Saturday (Enomoto)

Weekend

  • Fiber noise cancellation work at PSL on Saturday (Enomoto, Sugimoto)
  • Xarm ALS hand over to IR using TR (Enomoto)

Monday Morning

  • ITMY damping (Okutomi)
  • Type A work (Fujii)
  • ITMX damping (Ushiba)
  • Cryo cooler valve exchange (Kimura, Ushiba)
  • SR3 TF measurement (Fabian)
  • Automation for SR3 and SRM (Shoda)
  • Noise source by cable or something in the center room (Yokozawa)
  • Setting magnet meter at Y end (Yokozawa)


Standing issues

  • Try FPPRMI: with stable 3f signals and ALS extra range, FPPRMI may fix the glitches?
  • Fast shut off feature on type-A after lockloss not to ring (real time model change, Stefan)
  • Y-arm lock
    • ETMY suspension control
    • ITMY damping
      • One IM magnet is broken. Need a different strategy. Use MN ? (Yamada, Okutomi)
  • DRMI lock stability
    • Model HOM-PHD signal distortion (Aso, Kokeyama)
    • Search for better Gouy phase in PRC
  • Initial alignment automation (Nakano)
  • IFO configuration Guardian (Kokeyama)
  • SDF for all the VIS (Shoda, Okutomi)
  • Type-A related
    • Implement BF stage control on ALIGNED state on type-A guardian (Kokeyama)
    • United Guardian for all 4 suspensions (Okutomi)
    • Damping
    • Exchanging modified HPCD.
    • Type A: Feed forward technic to suppress extra motion (Nakano)
  • Type-B related
    • SR3 Yaw motion is too large (Fabian, Terrence)
  • Type-C related
    • OSEM characterization for OSTM (on going, Takahashi)
  • OMC
    • OMC characterization with control
  • Laser safety
    • Debug the laser safety guardian (Nakano)
  • AS tube installation on 7/30-31 (Michimura)
  • Valve unit exchange for ITMX on 7/26 for 1-2 hours (Kimura)
  • Fiber noise cancellation on Saturday (Enomoto, Sugimoto)
  • ITM noise measurement by PEM on 27th morning (Yokozawa).
  • IR QPD, centering on IR , green QPD at ETMY (Akutsu)
  • Exchanging laser source of oplev (Akutsu)

Meeting archive



Daily morning meeting

  • Date and time: Every weekday, 9AM
  • First ~10min in the morning meeting, as short as possible
  • Location: Control room and Fan hut connected by eZuce

2019/7/26(Fri.)

Schedule

  • ~7/31: Trial for DRMI with polarization.
  • 7/6~: Trial for mass lock
  • ITMX
  • ETMX
  • ITMY
  • ETMY
  • Long term:
    • 7/1-8/9: FPMI/DRFPMI commissioning
    • 8/12-10/4: ASC
    • 10/7-11/15: Post Commissioning
    • 11/18-12/13: Noise hunting

Note

Night work

Weekend

Report of work

  • COM: Hand off to TRX was succeeded in!
  • ITMY: F0 motor on ITMY was stuck.
    • We decided to open the chamber to fix the motor.
    • One of the dropped magnet of IM on ITMY will be glued.
    • It seemed to be another magnet was off.
  • OMC axis was not perfect, but it is turned out not easy to tune the axis by hand without jig.

Work plan

  • Remaining TF of ITMY will be measured this morning.
  • Cryo cooler valve exchange (Kimura, Ushiba)
  • Venting will start.
  • Type A work (Fujii)
  • SR3 TF measurement (Fabian)
  • Automation for SR3 and SRM (Shoda)
  • Noise source by cable or something in the center room (Yokozawa)
  • Setting magnet meter at Y end (Yokozawa)

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  



Weekly meeting

No.

Date

Agenda

Schedule

Minute

Files

76

2019/7/23

Agenda

See agenda page

Minute

75

2019/7/16

Agenda

See agenda page

Minute

74

2019/7/2

Agenda

See agenda page

Minute

73

2019/6/25

Agenda

See agenda page

Minute

72

2019/5/28

Agenda

See agenda page

Minute

71

2019/5/21

Agenda

See agenda page

Minute

70

2019/5/14

Agenda

See agenda page

Minute

69

2019/5/7

Agenda

See agenda page

Minute

68

2019/4/23

Agenda

See agenda page

Minute

67

2019/4/16

Agenda

See agenda page

Minute

66

2019/4/9

Agenda

See agenda page

Minute

65-1

2019/4/2

Integrated Type-A meeting

65

2019/4/2

Agenda

See agenda page

Minute

64

2019/3/26

Agenda

See agenda page

Minute

file

63

2019/3/11

Agenda

See agenda page

Minute

62

2019/3/5

Agenda

See agenda page

Minute

61

2019/2/19

Agenda

See agenda page

Minute

60

2019/2/5

Agenda

See agenda page

Minute

59

2019/1/29

Agenda

Minute

58

2019/1/22

Agenda

Minute

57

2019/1/8

Agenda

Minute

56

2018/12/25

Agenda

Minute

55

2018/12/17

Agenda

Minute

54

2018/12/11

Agenda

Minute

53

2018/12/4

Agenda

Minute

52

2018/11/27

Agenda

Minute

51

2018/11/20

Agenda

Minute

50

2018/11/13

Agenda

Minute

49

2018/11/6

Agenda

Minute

48

2018/10/30

Agenda

Minute

47

2018/10/23

Agenda

Minute

46

2018/10/16

Agenda

Minute

45

2018/10/9

Agenda

Schedule

Minute

44

2018/10/2

Agenda

Schedule

Minute

43

2018/9/18

Agenda

Schedule

Minute

42

2018/9/4

Agenda

Schedule

Minute

41

2018/8/28

Agenda

Schedule

Minute

40

2018/8/21

Agenda

Schedule

Minute

39

2018/8/7

Agenda

Schedule

Minute

38

2018/7/31

Agenda

Schedule

Minute

37

2018/7/24

Agenda

Schedule

Minute

36

2018/7/17

Agenda

Schedule

Minute

35

2018/7/3

Agenda

Schedule

Minute

34

2018/6/26

Agenda

Schedule

Minute

33

2018/6/19

Agenda

Schedule

Minute

32

2018/6/12

Agenda

Schedule

Minute

31

2018/6/5

Agenda

Schedule

Minute

30

2018/5/22

Agenda

Schedule

Minute

29

2018/5/8

Agenda

Schedule

Minute

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1



Other meetings



Task list


Documents

Communication tools

Readiness for the X arm commissioning


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)