Differences between revisions 849 and 1576 (spanning 727 versions)
Revision 849 as of 2019-07-24 13:30:21
Size: 23183
Comment:
Revision 1576 as of 2019-11-15 13:34:38
Size: 26323
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
-----

=== Daily commissioning meeting ===
 * Time: 1PM everyday
 * Location: KAGRA control room
 * Remote participation: https://zoom.us/j/7631499341
<<TableOfContents(2)>>

-----

<<Anchor(1PMMeetings)>>
Line 11: Line 10:
== Today's work plan: 2019/11/15 1PM - 2019/11/16 1PM ==

=== Afternoon ===
 * ASC work for Y arm or X arm (Eleonora, Lucia, K.Tanaka)
 * Fixing phase noise cancel for both X, Y green (Nakano)
 * ISS noise measurement (Yoshioka, Miyakawa)
 * PEM turn on vacuum pump aound 3pm (Yokozawa, Washimi)
 * Entering PSL shortly (Kokeyama)
 * Laser power for PCal needs EX alignment (Yamamoto)

=== Evening ===
 * FPMI lock (Nakano)
 
=== Weekend ===
 * FPMI lock (Nakano)
 * VIS noise budget (Lucia, Ushiba)
 * Type A measurement on Saturday morning (Fujii)

=== Nov. 18 Morning ===
 * ASC work for FPMI (Eleonora, Lucia, K.Tanaka)
 * Double demodulation work (Kokeyama, Koyama)
 * PEM work around ISS table (Yokozawa)
 * OMC assembling (Aso)

||Configuration||11/18 silent-run slot||Morning ||11/15 Afternoon ||Evening ||Weekend ||
|| || || || || || ||
||PSL || || || || || ||
||IMC || || || || || ||
||X-arm ||ASC || ||ASC || || ||
||Y-arm ||ASC || || || || ||
||MICH || || || || || ||
||ALS-DARM || || || || || ||
||FPMI ||ASC || ||Nakano ||Nakano || ||
||PFPMI || || || || || ||
|| || || || || || ||
||BS || || || || || ||
||ITMX || || || || || ||
||ITMY || || || || || ||
||ETMX || || || || || ||
||ETMY || || || || || ||
||PRM || || || || || ||
||PR2 || || || || || ||
||SRM || || || || || ||
||REFL port || || ||ASC || || ||
||POP port || || ||ASC || || ||
||AS port || || || || || ||


------

<<Anchor(Meetings)>>
== Meetings ==

 . [[#1PMMeetings|Daily Meeting]]
  * Zoom 1 URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]]
  * Time: 4PM, everyday
  * Location: KAGRA control room

 . [[#MorningMeetings|Morning Meeting]]
  * Zoom 1 URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]]
  * Time: 9AM, everyday
  * Location: KAGRA control room

 . [[#WeeklyMeetings|Weekly Meetings]]
  * Zoom 2 URL: [[https://zoom.us/j/6676627462|https://zoom.us/j/6676627462]]
  * Time: 11AM, every Tuesday
  * Location: 2F large meeting room

 . [[#OtherMeetings|Other Extra Meetings]]
Line 13: Line 81:
== Today's work plan: 2019/7/24 1PM - 2019/7/25 1PM ==
Commissioning leader: Miyakawa (22nd-26th)

=== Afternoon ===
 * Replacing LVDT driver on SR3(Fabian)
 * Single arm locking (Stefan)
 * Fix AC to stablize temeparute (Miyoki)
 * ITMY damping (Okutomi)
 * Maintenance for Ondotori (Yokozawa, T. Tanaka)
 * ALS model medication (Enomoto, Sugimoto)

=== Evening ===
 * ALS hand over to IR using TR (Nakano, Enomoto)
 * DRFPMI lock (Nakano, Enomoto)

=== Weekend ===

=== Morning ===
 * ITMY damping (Okutomi)
 * Type A work (Fujii)
 * SR3 OSEM check (Fabian)
 * DGS maintenance for arm or srm.
  * Adding BIO card to k1als0, k1ioo1.
 * Exchanging old type modified HPCD. (Ushiba, Takahashi)
 * ISS control servo (Yoshioka, Kokeyama)
== Working people assignment ==
 * [[https://teamup.com/kswnmta8p18h6u1uab|KAGRA Commissioning Planner]]

== Schedule ==

 * Cryo cooler check on 8/5 (Kimura)
 * ITMX cooler stop on 8/6 (CRY)
 * Y arm will be available from 8/8~
 * ETMX warm up 8/9 (CRY)
 * ETYY cooling (CRY)
Line 41: Line 94:
 * Try FPPRMI: with stable 3f signals and ALS extra range, FPPRMI may fix the glitches?
 * Fast shut off feature on type-A after lockloss not to ring (real time model change, Stefan)
 * Y-arm lock
  * ETMY suspension control
  * ITMY damping
   * One IM magnet is broken. Need a different strategy. Use MN ? (Yamada, Okutomi)
  *

[[https://paper.dropbox.com/doc/VIS-Commissioning-Task-List--Ajp3qd1D4Z0~YpldRCShrQx6AQ-RKcNXfMFrqOtTAPU48qQf|VIS Task List]]

 * PEM - measured data sharing (Washimi, Yokozawa)
 * How to control the PSL temperature when people enters the room (Miyoki)
Line 49: Line 101:
  * Model HOM-PHD signal distortion (Aso, Kokeyama)   * 3f transition
Line 51: Line 103:
 * Initial alignment automation (Nakano)
 * IFO configuration Guardian (Kokeyama)
 * Type-A related
 * PRFRMI: with stable 3f signals and ALS extra range, FPPRMI may fix the glitches?

 * VIS related
Line 57: Line 109:
  * Exchanging modified HPCD.
Line 59: Line 110:
 * Type-B related
  * SR3 Yaw motion is too large (Fabian, Terrence)
 * Type-C related
  * OSEM characterization for OSTM (on going, Takahashi)
 * OMC
  * Check the OMC on the AS table
 * Laser safety
  * Debug the laser safety guardian (Nakano)

 * IR QPD, centering on IR , green QPD at ETMY (Akutsu)

 * AS tube installation on 7/30-31 (Michimura)
 * Valve unit exchange for ITMX on 7/26 for 1-2 hours (Kimura)
 * Fiber noise cancellation on Saturday (Enomoto, Sugimoto)

------
 
 

== Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]
 * [[https://docs.google.com/spreadsheets/d/1DSltWg18KrwnfkVJmSm09TkQ82aQ5lHAdaC9uCozGC0/edit?usp=sharing|Preparation for joining O3]]

-----
<<Anchor(Schedule)>>
=== Schedule ===




-----
== Working people assignment ==
 * [[https://teamup.com/kswnmta8p18h6u1uab|KAGRA Commissioning Planner]]

== Readiness for the X arm commissioning ==
 * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]]

  
{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==


}}}
-----

<<Anchor(Meetings)>>

== Meetings ==

==== Daily Meetings (9AM, 1PM) ====
Zoom URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]]

==== Weekly Meetings (Tuesday 11AM) ====
Zoom URL: [[https://zoom.us/j/6676627462|https://zoom.us/j/6676627462]]
  * Automation script for damping for calm down phase

  * PR2 & PRM oplev wind shield, PR3 LS oplev centering
  * Wind shield for PR2 and PRM (Enomoto)

 * For ASC things
  * Fix clipping at IFI with IFO (Kokeyama)
  * Measure TF of VIS as ASC actuator (Okutomi)
  * One arm WFS test

 * ETMY strong damping (Lucia, Ushiba)
 * DAC non-linearity (http://klog.icrr.u-tokyo.ac.jp/osl/?r=10699)
 * QPD diagonalization ETMX and ETMY, for remote work (Akutsu)
 * Establishing investigation method for diagonalization using ETMY only (all VIS power)
 * Fix oplev noise for ITMY
 * Fix oplev noise for ITMX
 * Fix oplev gain for ETMY (Akutsu)
 * Covering wind shield for oplevs of iMC (Akutsu, or somebody)
 * Investigation for noise of length oplev noise for ITMs (VIS + CRY)
 * PD dark noise investigation (Kozakai)
 * Sensor correction for Type B by large motion like typhoon (Fabian)
 * Check for all PD or other circuits for grounding on table (Ushiba)
 * Gate valve test (Tomaru)
 * Vacuum pump noise measurement (Yokozawa)

 * Temperature stabilization due to fan off (Miyoki)


Line 119: Line 141:
<<Anchor(MorningMeetings)>>
== Daily morning meeting ==

 * Date and time: Every weekday, 9AM
 * First ~10min in the morning meeting, as short as possible
 * Location: Control room and Fan hut connected by eZuce


=== 2019/7/24(Wed.) ===

==== Schedule ====
 * ~7/31: Trial for DRMI with polarization.
 * 7/6~: Trial for mass lock

 * ITMX

 * ETMX

 * ITMY

 * ETMY


 * Long term:
  * 7/1-8/9: FPMI/DRFPMI commissioning
  * 8/12-10/4: ASC
  * 10/7-11/15: Post Commissioning
  * 11/18-12/13: Noise hunting


==== Note ====

==== Night work ====

==== Weekend ====

==== Report of work ====
 * Temperature drift affected IFO commissioning. So tried ALS signal handling off to TRX and TRY.
 * SR3 H2 noise investigation is still going on.
 * Suppressing 80mHz of yaw by feeding back the MN oplev signal was done.
 * OMC work for alignment. Control system was implemented.
 * temperature fluctuation at all the central area specially around BS for 0.6C with 20hours period.

==== Work plan ====
 * DGS maintenance
 * BIO cards installation.
 * Replacing RT-PCs of SR or PR
 * Modification of Type A model.
 * Temperature maintenance in the afternoon.
 * MZ work (Guiguo).
 * OMC work in the morning.
Line 174: Line 146:
---- -----
-----
Line 177: Line 150:
 * Date and time: Every Tuesday, 11AM
 * Location: Meeting room at Hokubukaikan, or Zoom
Line 182: Line 153:
||83||2019/11/12||[[KAGRA/Commissioning/Weekly/20191112/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20191112/Minute|Minute]]|| ||
||82||2019/10/15||[[KAGRA/Commissioning/Weekly/20191015/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20191015/Minute|Minute]]|| ||
||81||2019/10/8||[[KAGRA/Commissioning/Weekly/20191008/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20191008/Minute|Minute]]|| ||
||80||2019/10/1||[[KAGRA/Commissioning/Weekly/20191001/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20191001/Minute|Minute]]||[[attachment:KAGRA/Commissioning/20191001_ccommissioning.pdf|file]]||
||79||2019/9/3||[[KAGRA/Commissioning/Weekly/20190903/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190903/Minute|Minute]]|| ||
||78||2019/8/20||[[KAGRA/Commissioning/Weekly/20190820/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190820/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10561| File]]||
||77||2019/8/6||[[KAGRA/Commissioning/Weekly/20190806/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190806/Minute|Minute]]||||
Line 260: Line 238:
----
-----
-----
<<Anchor(OtherMeetings)>>
Line 284: Line 265:
-----
 
== Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]
 * [[https://docs.google.com/spreadsheets/d/1DSltWg18KrwnfkVJmSm09TkQ82aQ5lHAdaC9uCozGC0/edit?usp=sharing|Preparation for joining O3]]
-----
Line 294: Line 283:
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)



------
== for New members ==
 * [[KAGRA/Commissioning/ML|Joining commissioning Mailing List]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl

KAGRA Commissioning Wiki


Meeting archive

Today's work plan: 2019/11/15 1PM - 2019/11/16 1PM

Afternoon

  • ASC work for Y arm or X arm (Eleonora, Lucia, K.Tanaka)
  • Fixing phase noise cancel for both X, Y green (Nakano)
  • ISS noise measurement (Yoshioka, Miyakawa)
  • PEM turn on vacuum pump aound 3pm (Yokozawa, Washimi)
  • Entering PSL shortly (Kokeyama)
  • Laser power for PCal needs EX alignment (Yamamoto)

Evening

  • FPMI lock (Nakano)

Weekend

  • FPMI lock (Nakano)
  • VIS noise budget (Lucia, Ushiba)
  • Type A measurement on Saturday morning (Fujii)

Nov. 18 Morning

  • ASC work for FPMI (Eleonora, Lucia, K.Tanaka)
  • Double demodulation work (Kokeyama, Koyama)
  • PEM work around ISS table (Yokozawa)
  • OMC assembling (Aso)

Configuration

11/18 silent-run slot

Morning

11/15 Afternoon

Evening

Weekend

PSL

IMC

X-arm

ASC

ASC

Y-arm

ASC

MICH

ALS-DARM

FPMI

ASC

Nakano

Nakano

PFPMI

BS

ITMX

ITMY

ETMX

ETMY

PRM

PR2

SRM

REFL port

ASC

POP port

ASC

AS port


Meetings


Working people assignment

Schedule

  • Cryo cooler check on 8/5 (Kimura)
  • ITMX cooler stop on 8/6 (CRY)
  • Y arm will be available from 8/8~
  • ETMX warm up 8/9 (CRY)
  • ETYY cooling (CRY)


Standing issues

VIS Task List

  • PEM - measured data sharing (Washimi, Yokozawa)
  • How to control the PSL temperature when people enters the room (Miyoki)
  • DRMI lock stability
    • 3f transition
    • Search for better Gouy phase in PRC
  • PRFRMI: with stable 3f signals and ALS extra range, FPPRMI may fix the glitches?
  • VIS related
    • Implement BF stage control on ALIGNED state on type-A guardian (Kokeyama)
    • United Guardian for all 4 suspensions (Okutomi)
    • Damping
    • Type A: Feed forward technic to suppress extra motion (Nakano)
    • Automation script for damping for calm down phase
    • PR2 & PRM oplev wind shield, PR3 LS oplev centering

    • Wind shield for PR2 and PRM (Enomoto)
  • For ASC things
    • Fix clipping at IFI with IFO (Kokeyama)
    • Measure TF of VIS as ASC actuator (Okutomi)
    • One arm WFS test
  • ETMY strong damping (Lucia, Ushiba)
  • DAC non-linearity (http://klog.icrr.u-tokyo.ac.jp/osl/?r=10699)

  • QPD diagonalization ETMX and ETMY, for remote work (Akutsu)
  • Establishing investigation method for diagonalization using ETMY only (all VIS power)
  • Fix oplev noise for ITMY
  • Fix oplev noise for ITMX
  • Fix oplev gain for ETMY (Akutsu)
  • Covering wind shield for oplevs of iMC (Akutsu, or somebody)
  • Investigation for noise of length oplev noise for ITMs (VIS + CRY)
  • PD dark noise investigation (Kozakai)
  • Sensor correction for Type B by large motion like typhoon (Fabian)
  • Check for all PD or other circuits for grounding on table (Ushiba)
  • Gate valve test (Tomaru)
  • Vacuum pump noise measurement (Yokozawa)
  • Temperature stabilization due to fan off (Miyoki)


KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  



Weekly meeting

No.

Date

Agenda

Schedule

Minute

Files

83

2019/11/12

Agenda

See agenda page

Minute

82

2019/10/15

Agenda

See agenda page

Minute

81

2019/10/8

Agenda

See agenda page

Minute

80

2019/10/1

Agenda

See agenda page

Minute

file

79

2019/9/3

Agenda

See agenda page

Minute

78

2019/8/20

Agenda

See agenda page

Minute

File

77

2019/8/6

Agenda

See agenda page

Minute

76

2019/7/23

Agenda

See agenda page

Minute

75

2019/7/16

Agenda

See agenda page

Minute

74

2019/7/2

Agenda

See agenda page

Minute

73

2019/6/25

Agenda

See agenda page

Minute

72

2019/5/28

Agenda

See agenda page

Minute

71

2019/5/21

Agenda

See agenda page

Minute

70

2019/5/14

Agenda

See agenda page

Minute

69

2019/5/7

Agenda

See agenda page

Minute

68

2019/4/23

Agenda

See agenda page

Minute

67

2019/4/16

Agenda

See agenda page

Minute

66

2019/4/9

Agenda

See agenda page

Minute

65-1

2019/4/2

Integrated Type-A meeting

65

2019/4/2

Agenda

See agenda page

Minute

64

2019/3/26

Agenda

See agenda page

Minute

file

63

2019/3/11

Agenda

See agenda page

Minute

62

2019/3/5

Agenda

See agenda page

Minute

61

2019/2/19

Agenda

See agenda page

Minute

60

2019/2/5

Agenda

See agenda page

Minute

59

2019/1/29

Agenda

Minute

58

2019/1/22

Agenda

Minute

57

2019/1/8

Agenda

Minute

56

2018/12/25

Agenda

Minute

55

2018/12/17

Agenda

Minute

54

2018/12/11

Agenda

Minute

53

2018/12/4

Agenda

Minute

52

2018/11/27

Agenda

Minute

51

2018/11/20

Agenda

Minute

50

2018/11/13

Agenda

Minute

49

2018/11/6

Agenda

Minute

48

2018/10/30

Agenda

Minute

47

2018/10/23

Agenda

Minute

46

2018/10/16

Agenda

Minute

45

2018/10/9

Agenda

Schedule

Minute

44

2018/10/2

Agenda

Schedule

Minute

43

2018/9/18

Agenda

Schedule

Minute

42

2018/9/4

Agenda

Schedule

Minute

41

2018/8/28

Agenda

Schedule

Minute

40

2018/8/21

Agenda

Schedule

Minute

39

2018/8/7

Agenda

Schedule

Minute

38

2018/7/31

Agenda

Schedule

Minute

37

2018/7/24

Agenda

Schedule

Minute

36

2018/7/17

Agenda

Schedule

Minute

35

2018/7/3

Agenda

Schedule

Minute

34

2018/6/26

Agenda

Schedule

Minute

33

2018/6/19

Agenda

Schedule

Minute

32

2018/6/12

Agenda

Schedule

Minute

31

2018/6/5

Agenda

Schedule

Minute

30

2018/5/22

Agenda

Schedule

Minute

29

2018/5/8

Agenda

Schedule

Minute

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1



Other meetings



Task list


Documents

Communication tools

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)